Advertisement for Bid-Ozarks Technical Community College–Table Rock Campus (Hollister)
| December 7, 2011 11:00 am | to | January 5, 2012 2:00 pm |
Sealed Proposals for:
TABLE ROCK CAMPUS
Request for Proposal for Construction Management Services
OZARKS TECHNICAL COMMUNITY COLLEGE
10698 Historic Hwy 165
Hollister, Missouri 65673
PROJECT NO. 201104
Owner: Ozarks Technical Community College
1001 East Chestnut Expressway
Springfield, Missouri 65802
All endorsed “Proposals” for Construction Management at Risk Services shall be mailed to or delivered to the office of the Vice Chancellor for Administrative Services, Rob Rector, suite 204, Information Commons Building at Ozarks Technical Community College (Springfield Campus), 1001 E. Chestnut Expressway, Springfield, Missouri 65802, no later than 2:00 p.m., CST, Thursday, January 05, 2012 (time shall be determined by the clock in office IC 204).
Preliminary plans and specifications may be reviewed at the office of the Architect, Baron Design & Associates, LLC 1855 S. Ingram Mill, Suite 201, Springfield, Missouri 65804.
Direct all questions to the OTC College Architect, attention Harlan Hill, 417-447-4810, fax 417-447-4804.
A complete Request for Proposal information packet may be acquired from the office of the College Architect, 933 E. Central Street, Springfield, Missouri 65802, or information can be downloaded from the OTC website at www.otc.edu/facilities.php .
All interested parties must register their contact information in order to receive periodic updates and addenda. Register information by calling Harlan Hill, College Architect at 417-447-4810 or email at hillh@otc.edu .
The bidder understands that Ozarks Technical Community College reserves the right to award the contract to the lowest responsible bidder and to reject any or all bids and / or to waive any technicalities or informalities in the bidding.
BID SECURITY:
Bids are to be submitted on the Bid Form issued with the Construction Documents and must be accompanied by a Bid Guarantee (Bid Bond) equivalent to five percent (5%) of the amount of the bid. See Instructions to Bidders for additional information. Surety/Bonding Company must be acceptable to the Owner and be authorized to transact business in the state of Missouri.
PERFORMANCE BOND AND PAYMENT BOND:
A Performance Bond and Payment Bond are required of the successful Bidder in the amount of 100 percent of the contract.
PRE-BID CONFERENCE (Mandatory):
A pre-bid conference is scheduled for 2:00 p.m., Thursday, December 15, 2011, at the Town Hall, 312 Esplanade, Hollister, Missouri 65673. Weather permitting, a site visit will follow after the meeting.
SCHEDULE:
Bidders must submit a Work Schedule with their Bid.
BID PERIOD:
November 29, 2011 through January 05, 2012.
PREVAILING WAGES:
Prevailing wages shall be paid in accordance with the Missouri Division of Labor Standards, Annual Wage Order in effect at the time of construction.
TAX EXEMPT STATUS:
This project requires application of tax exempt status on behalf of the Owner.
PROJECT COMPLETION:
All Work for this project shall be substantially complete by June 1, 2013. In lieu of liquidated damages, OTC shall be entitled to recover its actual damages for delay.

