MSU 3-Month Look Ahead – April

  • News

Winter weather apparently does not want to give up its grip as cooler weather is setting in.  With the expectation of warmer weather coming and the end of the spring semester, the list of projects established for bidding continues to grow.  While we would like to have exact dates for all projects that will be bidding in the next 3 months, there are forces outside of our control that change dates as we get closer to issuing a project for bidding.  Please use the following list as a guide.  Accurate information will be posted on our website at: Construction Look Ahead – Planning Design & Construction.  The projects listed below are listed by their expected bid date.

 

Expansion of Parking Lot 39                           
Project Description:  A parking lot is to be constructed south of Kentwood Hall.  The design will include both asphalt and concrete options.

Consultant:  CJW Transportation Consultants
Estimated Construction Cost:  $400,000

Issue for Bid:  March 20, 2017
Bid Opening:  April 4, 2017
Award of Contract:  April 19, 2017
Start of Construction:  May 22, 2017

 

Renovate Computer Labs, Cheek Hall  
Project Description:  The existing Cheek Hall computer lab on the first floor shall be reconfigured to allow for the construction of a new Computer Sciences computer lab, resulting in two separate computer labs.  The entire area currently occupied by the open computer lab will be renovated to provide for the two labs plus support area. This project is to be completed during the summer of 2017.

Consultant:  Dake | Wells Architecture
Estimated Construction Cost:  $400,000

Issue for Bid:  March 23, 2017
Bid Opening:  April 6, 2017
Award of Contract:  April 19, 2017
Start of Construction:  May 23, 2017

Computer Lab 150 Asbestos Removal, Cheek Hall                   
Project Description:  The existing computer lab and support areas within Cheek Hall will be completely renovated to create a new computer sciences classroom and support area along with a renovated computer services open computer lab and support areas.  The asbestos removal will occur during the renovation of the space.  The work will be the removal of all VAT tile and floor covering in the space.

Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $20,000

Issue for Bid:  March 23, 2017
Bid Opening:  April 6, 2017
Award of Contract:  April 19, 2017
Start of Construction:  May 27, 2017

Re-Apply Paint Finish, Craig Hall

Project Description:  The purpose of this project is to remove the existing paint that is peeling at the 3rd floor corridor surfaces and to reinstall new paint to these surfaces.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $185,000
Issue for Bid:  March 30, 2017
Bid Opening:  April 13, 2017

Award of Contract:  May 18, 2017
Start of Construction:  May 22, 2017

Wyrick Plaza Improvements, Landscaping and Plazas

Project Description:  This project will construct a new landscaped plaza are located east of the fountain on the West Mall of the Campus.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $230,000
Issue for Bid:  April 4, 2017
Bid Opening:  April 18, 2017

Award of Contract:  May 18, 2017
Start of Construction:  May 22, 2017

Install Second Floor Carpet, Meyer Library

Project Description:  This project will remove and replace the existing carpet on the second floor of the library.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $75,000
Issue for Bid: April 4, 2017
Bid Opening:  April 18, 2017

Award of Contract:  April 20, 2017
Start of Construction:  Upon Award

Asbestos Removal, Hill Hall

Project Description:  The purpose of this project is to abate any hazardous materials from the project prior to the commencement of construction on the main project.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $150,000
Issue for Bid:  April 6, 2017
Bid Opening:  April 20, 2017

Award of Contract:  May 18, 2017
Start of Construction:  June 1, 2017

Closet Improvements, Hammons House

Project Description:  This project will separate the existing wardrobe area into to two closet spaces with clothes rods in student rooms.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $80,000
Issue for Bid: April 11, 2017
Bid Opening:  April 25, 2017

Award of Contract:  May 18, 2017
Start of Construction:  May 22, 2017

 

Floor Finish Replacement, Scholars House

Project Description:  This project will replace existing floor finishes in student suites on floors two through four.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $150,000
Issue for Bid:  April 11, 2017
Bid Opening:  April 25, 2017

Award of Contract:  May 18, 2017
Start of Construction:  May 29, 2017

Renovation of the Third Floor, Professional Building

Project Description:  Renovate classrooms and labs for genetics, physiology, anatomy, biosciences, masters of public health, and the GSA workroom and lab preparation areas.
Consultant:  Hastings & Chivetta
Estimated Construction Cost:  $800,000
Issue for Bid: April 13, 2017
Bid Opening:  April 27, 2017

Award of Contract:  May 18, 2017
Start of Construction:  May 22, 2017

Install Septic System, Baker Observatory

Project Description:  Install a septic system capable of accommodating 125 people and a small catering kitchen.
Consultant:  CFS Engineers
Estimated Construction Cost:  $40,000
Issue for Bid:  April 13, 2017
Bid Opening:  April 27, 2017

Award of Contract:  May 4, 2017
Start of Construction:  Upon award

Refinish Racquetball Courts, Plaster Sports Complex

Project Description:  Refinish 12 racquetball courts and repair select areas of damaged or bad spots of the wood floors. Repair and replace damaged areas of the walls and ceilings.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $50,000
Issue for Bid:  April 18, 2017
Bid Opening:  May 2, 2017

Award of Contract:  May 4, 2017
Start of Construction:  May 22, 2017

Renovation of Human Resources, Carrington Hall

Project Description:  Upgrade the public areas and provide additional offices within the existing footprint.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $70,000
Issue for Bid:  April 20, 2017
Bid Opening:  May 4, 2017

Award of Contract:  May 8, 2017
Start of Construction:  Upon Award

Replace Boiler, Kentwood Hall
Project Description:  This project replaces the boilers located in the basement with new energy efficient boilers. The project will also have alternates to relocate an existing chilled water pump and re-insulate the hydronic piping within the mechanical room.

Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $216,000

Issue for Bid:  April 27, 2017
Bid Opening:  May 11, 2017
Award of Contract:  June 23, 2017
Start of Construction:  July 5, 2017

Rigging Point Installation, Juanita K. Hammons Hall for the Performing Arts
Project Description:  This project will install engineered rigging points above the audience seating area for an upcoming production in 2018. Installation may require the removal of existing roofing.

Consultant:  J&M Engineering
Estimated Construction Cost:  $50,000

Issue for Bid:  May 11, 2017
Bid Opening:  May 25, 2017
Award of Contract:  June 23, 2017
Start of Construction:  Upon Award

 

Improvements to the PT Clinic, McQueary Family Health Sciences Hall
Project Description:  This project will modify building structure and install a ceiling-mounted overhead body-weight supported ambulation system.
Consultant:  J&M Engineering
Estimated Construction Cost:  $65,000
Issue for Bid:  May 16, 2017
Bid Opening:  May 30, 2017
Award of Contract:  June 23, 2017
Start of Construction:  Upon Award

 

Laundry Room Modifications, Woods House
Project Description:  This project will remove existing VCT flooring in laundry room 1001.  The concrete floor will be repaired as needed and sealed.  A laundry alert system will be installed to accommodate new washer and dryers.

Consultant:   MSU Planning, Design & Construction
Estimated Construction Cost: $20,000

Issue for Bid:  May 23, 2017
Bid Opening:  June 6, 2017
Award of Contract:  June 8, 2017
Start of Construction:  June 19, 2017

Missouri State University could not continue to improve our campus without the support of the construction industry in southwest Missouri. We appreciate your assistance in helping us build a better Missouri State University.

 

 

 