Skip to content

Contact SCA

Springfield Contractors Association
1313 N. Nias
Springfield MO 65802
Phone: 417-862-1313

Click to Email Us

Office Hours:
Monday-Thursday, 8:30am-4:30pm
Friday, 8:30am-Noon

Map to Our Office:

View Larger Map

MSU 3 month Look Ahead

  • News

The New Year is well under way now and our department is busily trying to prepare projects for 2016.  Our focus is turning to summer work.  Below you will find a list of projects that are either currently out for bid, or are scheduled to bid over the next few months.  As always, some dates may change on these projects as we get closer to the time frame for the release of the project.  Our web site at: Construction Look Ahead – Planning, Design & Construction – Missouri State University will provide you with the latest information.  We encourage you to check this web site should you be interested in any of these projects.  If you need further information on any of them, please do not hesitate to contact our office.

 

The projects currently scheduled include:

 

Rectify Water Damage, JQH Arena

 

Project Description:  Rectify the water damage which occurred in the basement locker rooms at JQH Arena. The work will be split into multiple phases to accommodate the athletic schedules. Work includes installation of new insulation, drywall, wall and floor preparation for finishes, carpet, cove base, toe kicks for the lockers and cabinets, repairing millwork and paint.

Consultant:  Planning, Design & Construction
Estimated Construction Cost:  $100,000.00
Issue for Bid:  January 26, 2016
Bid Opening:  February 9, 2016
Award of Contract:  February 17, 2016
Start of Construction:  April 4, 2016

 

 

Bathroom Renovation, Blair House

Project Description:  The University is renovating the suite bathrooms on floors 1 through 9.

Consultant:  Treanor Architects
Estimated Construction Cost:  $1,200,000.00
Issue for Bid:  February 15, 2016
Bid Opening:  March 1, 2016
Award of Contract:  March 16, 2016
Start of Construction:  May 16, 2016

 

 

Replace Air Handling Units, Hutchens House

 

Project Description:  This project installs new air handling units in the common spaces in Hutchens House.

Consultant:  Planning, Design & Construction
Estimated Construction Cost:  $200,000.00
Issue for Bid:  February 16, 2016
Bid Opening:  March 1, 2016
Award of Contract:  March 16, 2016
Start of Construction:  April 2016

 

 

Improve District Chilled Water System, Campus Utilities

 

Project Description:  This project installs additional sections of distribution piping, and connects Kings Street Annex to the District Chilled Water System.

Consultant:  Ross and Baruzzini
Estimated Construction Cost:  $1,075,000.00
Issue for Bid:  February 9, 2016
Bid Opening:  March 3, 2016
Award of Contract:  March 16, 2016
Start of Construction:  April 2016

 

 

FY16 Preventative Parking Lot Maintenance

 

Project Description:  Repair, seal and restripe parking lots at the Springfield campus.

Consultant:  Planning, Design & Construction

Estimated Construction Cost:  $200,000.00
Issue for Bid:  Feb. 18, 2016
Bid Opening:  March 3, 2016
Award of Contract:  March 31, 2016
Start of Construction:  May 16, 2016

 

Mezzanine Improvements, Sunvilla Tower, Springfield Campus

 

Project Description:  Improve existing common area in student residential apartment tower. Scope of work to include insulated glazing replacement, existing storefront system waterproofing, general carpentry, terrazzo flooring improvements, painting, new stainless steel handrails, acoustical ceiling tile replacement, and electrical upgrades.

Consultant:  Planning, Design & Construction
Estimated Construction Cost:  $177,210.00
Issue for Bid:  March 1, 2016
Bid Opening:  March 15, 2016
Award of Contract:  April 20, 2016
Start of Construction:  May 16, 2016

 

 

Install Fire Suppression System, Garnett Library & Putnam Student Center, West Plains Campus

 

Project Description: Install fire suppression system in Garnett Library and Putnam Student Center on the West Plains Campus. Upgrade existing fire panel to support/include new suppression system.

Consultant:  TBD
Estimated Construction Cost:  $175,000.00
Issue for Bid:  March 22, 2016
Bid Opening:  April 5, 2016
Award of Contract:  April 20, 2016

Start of Construction:  May 16, 2016

 

 

Update Fire Protection in Rooms, Hutchens House

 

Project Description: Upgrade student room smoke detectors and related fire protection devices to be addressable units.

Consultant:  TBD
Estimated Construction Cost:  $185,000.00
Issue for Bid:  March 24, 2016
Bid Opening:  April 7, 2016
Award of Contract:  April 20, 2016

Start of Construction:  May 16, 2016

 

 

New Elevator Installation, Kentwood Hall

 

Project Description:  The University is replacing the existing elevator and constructing a new stair tower.

Consultant:  Butler, Rosenbury & Partners
Estimated Construction Cost:  $1,200,000.00
Issue for Bid:  March 24, 2016
Bid Opening:  April 7, 2016
Award of Contract:  April 20, 2016
Start of Construction:  May 16, 2016

 

Our deep appreciation continues to the construction community in southwest Missouri.  Through you, we continue to build a better Missouri State University.  Thanks for your help and we look forward to having a rewarding 2016.

 

 

 

Back To Top