MSU May 3-Month Construction Look Ahead

May is upon us and our summer construction season will be here shortly.  Many of the projects that will start immediately following the completion of the spring semester have been bid and are the contractors are actively preparing to begin construction on campus.  This month’s 3-month look ahead is shorter as many of our summer projects have now been bid.

The list below is our best projection as to the expected timeline for projects that will be bidding through July.  We continue to offer this list in hopes that it helps the contracting community to understand what is ahead for construction activities here on our campuses.  While this list is as complete as we know it today, additional projects will be added to the schedule within the next three months.  We are working on these projects but do not have timeframes established for these today.  For a more accurate listing of planned projects, please visit our website at: Construction Look Ahead – Planning, Design & Construction – Missouri State University.  This listing will be updated as projects are added.

We welcome your interest in our projects.  We want to be of service to the construction community.  If you have any questions or suggestions, we’d love to hear from you.  You are welcome to call us at 417-836-5101 or send me an email.  Good communications always lead to better projects.  As always, we are working together to build a better Missouri State University.

 

Relocate Sanitary Sewer – Meyer Library

Project Description: Relocate the sanitary sewer at Meyer Library. The project relocates approximately 200 feet of sanitary sewer from Meyer Library, installs 1 new manhole, and restores pavement. Construction is slated to occur early summer 2015.  This work is being done in anticipation of the Glass Hall Addition and Renovation project.

Consultant: CJW Transportation Consultants, LLC
Estimated Construction Cost: $50,000.00
Issue for Bid: April 23, 2015
Bid Opening: May 7, 2015
Award of Contract: May 12, 2015
Start of Construction: May 18, 2015

 

Job Order Contract – Plumbing

Project Description: Bids will be accepted for an annual contract which will allow the University to accomplish plumbing repairs and replacements on an on-call basis.  The cumulative total of all individual projects under this contract may not exceed $200,000 per fiscal year.  This annual contract allows for two additional one-year renewals.  Work under this contract may be done on University properties located in Douglas, Greene, Howell, Jasper, Laclede, Newton, Polk, Taney, Webster, and Wright counties.

Consultant: Planning, Design & Construction
Estimated Construction Cost: $200,000
Issue for Bid: April 30, 2015
Bid Opening: May 21, 2015
Award of Contract: June 26, 2015
Start of Construction: July 1, 2015


Job Order Contract – Electrical

Project Description: Bids will be accepted for an annual contract which will allow the University to accomplish electrical repairs and replacements on an on-call basis.  The cumulative total of all individual projects under this contract may not exceed $200,000 per fiscal year.  This annual contract allows for two additional one-year renewals.  Work under this contract may be done on University properties located in Douglas, Greene, Howell, Jasper, Laclede, Newton, Polk, Taney, Webster, and Wright counties.

Consultant: Planning, Design & Construction
Estimated Construction Cost: $200,000.00
Issue for Bid: April 30, 2015
Bid Opening: May 21, 2015
Award of Contract: June 26, 2015
Start of Construction: July 1, 2015

 

Job Order Contract – Pipe Insulation

Project Description: Bids will be accepted for an annual contract which will allow the University to accomplish pipe insulation repairs and replacements on an on-call basis.  The cumulative total of all individual projects under this contract may not exceed $200,000 per fiscal year.  This annual contract allows for two additional one-year renewals.  Work under this contract may be done on University properties located in Douglas, Greene, Howell, Jasper, Laclede, Newton, Polk, Taney, Webster, and Wright counties.

Consultant: Planning, Design & Construction
Estimated Construction Cost: $200,000.00
Issue for Bid: April 30, 2015
Bid Opening: May 21, 2015
Award of Contract: June 26, 2015
Start of Construction: July 1, 2015

 

Modifications for Freezer, Garst Dining Center

Additional freezer storage space is needed at the Garst Dining Center.  In order to accommodate a new outdoor freezer, a new pad will be provided and existing site features modified as required.  Work for the project includes expansion of an existing screen wall, a new concrete pad, and electrical service for operation of a new freezer.  Work should begin upon award of a contract.

Consultant:  Smith-Goth Engineers, Inc.
Estimated Construction Cost:  $150,000
Issue for Bid:  May 12, 2015
Bid Opening:  May 26, 2015
Award of Contract:  June 26, 2015
Start of Construction:   June 29, 2015

 

Tornado Community Storm Shelter

Project Description: This project constructs a FEMA rated safe room west of the existing Sunvilla Tower residence hall.

Consultant: The Lawrence Group
Estimated Construction Cost: $1,500,000
Issue for Bid: May, 2015 (tentative)
Bid Opening: June, 2015 (tentative)
Award of Contract: July, 2015 (tentative)
Start of Construction: TBD

Work continues on our Glass Hall project and we anticipate this project being available for bidding in August with a September bid date.  Depending upon the actions in Jefferson City, there may be more significant renovations that will be planned for construction starting in May of 2016.  We will keep you informed as progress develops on these projects.

 

Thank you.