EFIS & Masonry Restoration NKM Building-Ozarks Technical Community College

Ozark Technical Community College
EFIS & MASONRY RESTORATION FOR NORMAN K. MYERS TECHNICAL EDUCATION CENTER

All endorsed Proposals for EFIS & MASONRY RESTORATION FOR NORMAN K. MYERS TECHNICAL EDUCATION CENTER shall be mailed to or delivered to Blayne Radford, Operations Center 933 E. Central Street at Ozarks Technical Community College (Springfield Campus), Springfield, Missouri 65802, no later than 11:00 a.m., CST, Friday, April 27th, 2018 (time shall be determined by the clock in College Architects office). All received and qualified proposals will be opened and read aloud publicly.

Construction Drawings and Specifications will be available on April 11, 2018 and may be obtained through Springfield Blueprint, 219 E. Pershing, Springfield, Missouri 65806. (417) 869-7316. One (1) set of Documents will be issued upon a refundable deposit of seventy five dollars ($75.00) for each set. Mailing fees would be in addition to the $75.00 and is non refundable. Additional sets or electronic copies will be available for purchase. A full refund will be made for each set of construction documents returned in good condition, provided they are returned within 30 calendar days of the bid date.

Direct all questions to Architect:
Hood-Rich Architecture, 400 South Ave, Suite 300, Springfield, Missouri 65806
Attention: Jim Lohmeyer, 417-862-4483, ext. 103, or Brandon Hoch, ext 115.

The bidder understand that Ozarks Technical Community College reserves the right to award the contract to the lowest responsible bidder and to reject any or all bids and / or to waive any technicalities or informalities in the bidding.

BID SECURITY:

Bids are to be submitted on the Bid Form issued with the Construction Documents and must be accompanied by a Bid Guarantee (Bid Bond) equivalent to five percent (5%) of the amount of the bid. See Invitation to Bid for additional information. Surety/Bonding Company must be acceptable to the Owner and be authorized to transact business in the estate of Missouri.

PERFORMANCE BOND AND PAYMENT BOND:

A Performance Bond and Payment Bond are required of the successful Bidder in the amount of 100 percent of the contract.

PRE-BID CONFERENCE:

A pre-bid conference is scheduled for 1:30 p.m., Thursday, April 19th, 2018, beginning at the offices of the College Architect, Operations Center, 933 E. Central Avenue, Springfield, Missouri 65802.

SCHEDULE:

Pre-Bid Meeting: Thursday, April 9th, 2018 at 1:30 p.m.

Bid-Date and Time: Friday, April 27th, 2018 at 11:00 a.m.

Intended Award Date: May 2018

Expected Construction Start Date: June, 2018

Intended Construction Completion Date: Monday, August 13th, 2018

BID PERIOD:

April 11, 2018 through April 27, 2018.

PREVAILING WAGES:

Prevailing wages shall be paid in accordance with the Missouri Division of Labor Standards, Annual Wage Order in effect at the time of construction.

E-VERIFY:

Bidder shall furnish an affidavit and documentation affirming their company is enrolled in and participates in EVerify/ Basic Pilot and an affidavit stating the business does not knowingly employ illegal aliens.

TAX EXEMPT STATUS:

This project requires application of tax-exempt status on behalf of the Owner.

SUBSTANTIAL COMPLETION:

All Work for this project shall be substantially complete by August 13, 2018.

LIQUIDATED DAMAGES:

Failure to achieve the specified date of Substantial Completion will result in liquidated damages of $1,500 per day assessed to the Contractor until the date the Architect certifies the Final Pay Request.

Back To Top