MSU 3-Month Look Ahead – March

  • News

Spring is in the air and we are gearing up for a busy summer here on the Missouri State University campus.  The following is a list of projects that will be bidding over the next 3 months.  Some of these projects will extend beyond the summer into the academic year while others will need to be completed prior to the start of the fall semester in August.

 

Some of the dates below have yet to be established, and some dates listed here may change. Our web site at: Construction Look Ahead – Planning, Design & Construction – Missouri State University will provide you with the latest information.  We encourage you to check our website periodically for the latest in project dates and to be kept informed of any additions that may occur. The projects are listed in the order of the planned bid dates.

 

Expansion of Parking Lot 39                           
Project Description:  A parking lot is to be constructed south of Kentwood Hall.  The design will include both asphalt and concrete options.

Consultant:  CJW Transportation Consultants
Estimated Construction Cost:  $400,000

Issue for Bid:  March 20, 2017
Bid Opening:  April 4, 2017
Award of Contract:  April 19, 2017
Start of Construction:  April 24, 2017

Improvements to the PT Clinic, McQueary Family Health Sciences Hall                      
Project Description:  This project will modify building structure and install a ceiling-mounted overhead body-weight supported ambulation system.
Consultant:  J&M Engineering
Estimated Construction Cost:  $65,000
Issue for Bid:  March 28, 2017
Bid Opening:  April 11, 2017
Award of Contract:  April 2017
Start of Construction:  Upon Award

 

Renovation of Human Resources, Carrington Hall

Project Description:  Upgrade the public areas and provide additional offices within the existing footprint.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $70,000
Issue for Bid:  March 30, 2017
Bid Opening:  April 13, 2017

Award of Contract:  April 17, 2017
Start of Construction:  May 22, 2017

 

Third Floor Corridor, Craig Hall

Project Description:  The purpose of this project is to remove the existing paint that is peeling at the 3rd floor corridor surfaces and to reinstall new paint to these surfaces.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  TBD
Issue for Bid:  March 30, 2017
Bid Opening:  April 13, 2017

Award of Contract:  May 18, 2017
Start of Construction:  Upon award

Install Draperies, Sunvilla Tower
Project Description:  This project will provide and install new draperies and hardware. The existing sheers will be reused.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $120,000
Issue for Bid:  April 4, 2017
Bid Opening:  April 18, 2017

Award of Contract:  May 18, 2017
Start of Construction:  June 2017

Install Second Floor Carpet, Meyer Library

Project Description:  This project will remove and replace the existing carpet on the second floor of the library.
Consultant:  MSU Planning, Design & Construction.
Estimated Construction Cost:  $75,000
Issue for Bid: April 4, 2017
Bid Opening:  April 18, 2017

Award of Contract:  April 19, 2017
Start of Construction:  May 22, 2017

Wyrick Plaza Improvements, Landscaping and Plazas

Project Description:  This project will construct a new landscaped plaza are located east of the fountain on the West Mall of the Campus.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $230,000
Issue for Bid:  April 4, 2017
Bid Opening:  April 18, 2017

Award of Contract:  May 18, 2017
Start of Construction:  June 2017

Asbestos Removal, Hill Hall

Project Description:  The purpose of this project is to abate any hazardous materials from the project prior to the commencement of construction on the main project.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  TBD
Issue for Bid:  April 6, 2017
Bid Opening:  April 20, 2017

Award of Contract:  May 18, 2017
Start of Construction:  June 1, 2017

Computer Lab Renovations, Cheek Hall                      
Project Description:  The existing Cheek Hall computer lab on the first floor shall be reconfigured to allow for the construction of a new Computer Sciences computer lab, resulting in two separate computer labs.  The entire area currently occupied by the open computer lab will be renovated to provide for the two labs plus support area. This project is to be completed during the summer of 2017.

Consultant:  Dake | Wells Architecture
Estimated Construction Cost:  $400,000

Issue for Bid:  April 6, 2017
Bid Opening:  April 20, 2017
Award of Contract:  May 18, 2017
Start of Construction:  May 22, 2017

Rigging Point Installation, Juanita K. Hammons Hall for the Performing Arts                         
Project Description:  This project will install engineered rigging points above the audience seating area for an upcoming production in 2018. Installation may require the removal of existing roofing.

Consultant:  J&M Engineering
Estimated Construction Cost:  $50,000

Issue for Bid:  April 6, 2017
Bid Opening:  April 23, 2017
Award of Contract:  April 25, 2017
Start of Construction:  May 22, 2017

 

Closet Improvements, Hammons House

Project Description:  This project will separate the existing wardrobe area into to two closet spaces with clothes rods in student rooms.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $80,000
Issue for Bid: April 11, 2017
Bid Opening:  April 25, 2017

Award of Contract:  May 18, 2017
Start of Construction:  May 22, 2017

Floor Finish Replacement, Scholars House

Project Description:  This project will replace existing floor finishes in student suites on floors two through four.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $150,000
Issue for Bid:  April 11, 2017
Bid Opening:  April 25, 2017

Award of Contract:  May 18, 2017
Start of Construction:  May 29, 2017

Install Septic System, Baker Observatory

Project Description:  Install a septic system capable of accommodating 125 people and a small catering kitchen.
Consultant:  CFS Engineers
Estimated Construction Cost:  $40,000
Issue for Bid:  April 13, 2017
Bid Opening:  April 27, 2017

Award of Contract:  May 2017
Start of Construction:  Upon award

Renovation of the Third Floor, Professional Building

Project Description:  Renovate classrooms and labs for genetics, physiology, anatomy, biosciences, masters of public health, and the GSA workroom and lab preparation areas.
Consultant:  Hastings & Chivetta
Estimated Construction Cost:  $800,000
Issue for Bid: April 13, 2017
Bid Opening:  April 27, 2017

Award of Contract:  May 18, 2017
Start of Construction:  May 22, 2017

Refinish Racquetball Courts, Plaster Sports Complex

Project Description:  Refinish 12 racquetball courts and repair select areas of damaged or bad spots of the wood floors. Repair and replace damaged areas of the walls and ceilings.
Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $50,000
Issue for Bid:  April 27, 2017
Bid Opening:  May 11, 2017

Award of Contract:  May 15, 2017
Start of Construction:  May 22, 2017

Replace Boilers, Kentwood Hall                      
Project Description:  This project replaces the boilers located in the basement with new energy efficient boilers. The project will also have alternates to relocate an existing chilled water pump and re-insulate the hydronic piping within the mechanical room.

Consultant:  MSU Planning, Design & Construction
Estimated Construction Cost:  $216,000

Issue for Bid:  April 27, 2017
Bid Opening:  May 11, 2017
Award of Contract:  June 23, 2017
Start of Construction:  July 5, 2017

Renovation to Create Office Space, Foster Recreation Center

Project Description:  This project involves the renovation of a storage room into an office space for student workers at Foster Recreation Center. There will be some modifications to the HVAC, sprinkler and electrical systems.
Consultant:  To Be Determined
Estimated Construction Cost:  $50,000
Issue for Bid:  May 4, 2017
Bid Opening:  May 18, 2017

Award of Contract:  May 30, 2017
Start of Construction:  June 5, 2017

Missouri State University prides itself in the service we provide to our students.  This pride reflects in our facilities.  We could not have the campus we have if it were not for the contractors in southwest Missouri.  We want to thank all the individuals and firms that work on our campus helping build a better Missouri State University.

 

If you have any questions on these projects or other projects, please give us a call or email us so we can work to answer your questions.