MSU Construction Look Ahead – March 2015

The following is a list of projects that we currently have planned for the next 3 months. Some of these bid in the next few days, but I have left them on the listing. Once again the projects have been arranged in chronological order by their bid date. If you compare this list to the one issued last month, you will find projects have been added that will bid within the next month or two. We encourage you to check our website for the latest schedule for our projects. You may find this here: Construction Look Ahead – Planning, Design & Construction – Missouri State University. The listing on the website will be the most up-to-date information we have. If a project comes along and needs to be bid within the current 3-month look ahead, it will be added to our website listing as soon as we have it scheduled.

This listing is provided as a service to the contracting community in an effort to allow planning to occur on your end. We always welcome your interest in our projects. If you have any questions about any of these projects or projects in general, please contact us. Our office number is 417-836-5101.

Tunnel Repairs
Project Description: Repair and/or replacement of existing structural concrete lids on campus utility tunnels. Work would be accomplished during the summer of 2015.

Consultant: JM Engineering
Estimated Construction Cost: $400,000.00
Issue for Bid: February 19, 2015
Bid Opening: March 5, 2015
Award of Contract: March 18, 2015
Start of Construction: April 1, 2015

FY15 Preventative Parking Lot Maintenance, Springfield Campus
Project Description: Maintenance and repair of several asphalt parking lots on the Springfield Campus. Work will include patching, painting, and striping asphalt parking lots.
Consultant: Planning, Design, and Construction
Estimated Construction Cost: $200,000
Issue for Bid: February 19, 2015
Bid Opening: March 5, 2015
Award of Contract: March 18, 2015
Start of Construction: May 18, 2015

Third Floor Renovation, Craig Hall
Project Description: New finishes are to be applied to existing surfaces in order to provide for better wayfinding on the third floor of Craig Hall. New signage and lighting will be a part of this project. Work would be accomplished during the summer of 2015.

Consultant: Dake | Wells Architecture
Estimated Construction Cost: $160,000
Issue for Bid: February 19, 2015
Bid Opening: March 5, 2015
Award of Contract: March 18, 2015
Start of Construction: May 26, 2015

Renovation of the Third Floor, Plaster Student Union – Phase III
Project Description: The parliamentary room in the Plaster Student Union will be renovated under this interior project. The finishes within the room will be updated and improvements will be made in the ability to have electronic presentations within the room. Work would be accomplished during the summer of 2015.
Consultant: Buxton, Kubik, Dodd Creative Inc.
Estimated Construction Cost: $245,000
Issue for Bid: February 17, 2015
Bid Opening: March 10, 2015
Award of Contract: March 18, 2015
Start of Construction: May 18, 2015

HVAC Modifications, Room 211, JVIC
Project Description: Project provides a new exhaust branch with (3) 8” snorkel drops in Room 211 at Jordan Valley Innovation Center for use by researchers. A new air control valve will be installed and the room air flow re-programmed to support the additional exhaust.
Consultant: Planning, Design and Construction
Estimated Construction Cost: $17,000.00
Issue for Bid: February 27, 2015
Bid Opening: March 19, 2015
Award of Contract: March 20, 2015
Start of Construction: March 30, 2015

Blair-Shannon Dining Center Renovation
Project Description: A reworking of the serving lines is planned for this limited renovation project. Modifications to the serving lines to allow for better traffic flow and access to different foods is planned. Work would be accomplished during the summer of 2015.

Consultant: Butler, Rosenbury & Partners
Estimated Construction Cost: $225,000
Issue for Bid: March 3, 2015
Bid Opening: March 26, 2015
Award of Contract: April 15, 2015
Start of Construction: June 1, 2015

Hammons Transitway
Project Description: Construct a multimodal transitway along John Q. Hammons Boulevard between Grand and Bear Avenue. Transitway will include a dedicated bus lane, bike paths, sidewalks and landscaping. Work would be accomplished during the summer of 2015.

Consultant: TranSystems
Estimated Construction Cost: $400,000.00
Issue for Bid: March 10, 2015
Bid Opening: March 31, 2015
Award of Contract: April 17, 2015
Start of Construction: May 18, 2015

Testing & Assessment Center, Meyer Library
Project Description: A new testing and assessment center will be constructed within the confines of the existing library spaces. This renovation will occur on the lower level in the original building. In addition, new office spaces will be created for the consolidation of departments from campus to the library. Work would be accomplished during the summer of 2015.

Consultant: Cannon Design, Inc.
Estimated Construction Cost: $700,000
Issue for Bid: March 19, 2015
Bid Opening: April 2, 2015
Award of Contract: April 15, 2015
Start of Construction: May 18, 2015

Construct New Lot 20A
Project Description: Additional parking is needed on campus to offset the loss of parking on campus due to building projects. This parking lot will be located Parking Lot 25 and Parking Lot 20 just south of the “satellite farm” on the west side of campus near Holland Avenue. Construction is slated to occur late spring/early summer 2015.

Consultant: CJW Transportation Consultants, LLC
Estimated Construction Cost: $200,000.00
Issue for Bid: March 19, 2015
Bid Opening: April 2, 2015
Award of Contract: April 15, 2015
Start of Construction: April 16, 2015
Scheduled Completion: No later than August 8, 2015

2015 ADA Modifications
Project Description: Modifications are being made around campus to improve accessibility for all. These include changes to restrooms, hardware, and exterior work. Work is to be accomplished during the summer of 2015.

Consultant: Planning, Design, and Construction
Estimated Construction Cost: To be Determined
Issue for Bid: March 24, 2015
Bid Opening: April 7, 2015
Award of Contract: April 15, 2015
Start of Construction: May 18, 2015

Job Order Contract – Plumbing
Project Description: Bids will be accepted for an annual contract which will allow the University to accomplish plumbing repairs and replacements on an on-call basis. The cumulative total of all individual projects under this contract may not exceed $200,000 per fiscal year. This annual contract allows for two additional one-year renewals. Work under this contract may be done on University properties located in Douglas, Greene, Howell, Jasper, Laclede, Newton, Polk, Taney, Webster, and Wright counties.

Consultant: Planning, Design & Construction
Estimated Construction Cost: $200,000
Issue for Bid: April 9, 2015
Bid Opening: April 30, 2015
Award of Contract: May 20, 2015
Start of Construction: July 1, 2015

Job Order Contract – Electrical
Project Description: Bids will be accepted for an annual contract which will allow the University to accomplish electrical repairs and replacements on an on-call basis. The cumulative total of all individual projects under this contract may not exceed $200,000 per fiscal year. This annual contract allows for two additional one-year renewals. Work under this contract may be done on University properties located in Douglas, Greene, Howell, Jasper, Laclede, Newton, Polk, Taney, Webster, and Wright counties.

Consultant: Planning, Design & Construction
Estimated Construction Cost: $200,000.00
Issue for Bid: April 9, 2015
Bid Opening: April 30, 2015
Award of Contract: May 20, 2015
Start of Construction: July 1, 2015

Job Order Contract – Pipe Insulation
Project Description: Bids will be accepted for an annual contract which will allow the University to accomplish pipe insulation repairs and replacements on an on-call basis. The cumulative total of all individual projects under this contract may not exceed $200,000 per fiscal year. This annual contract allows for two additional one-year renewals. Work under this contract may be done on University properties located in Douglas, Greene, Howell, Jasper, Laclede, Newton, Polk, Taney, Webster, and Wright counties.

Consultant: Planning, Design & Construction
Estimated Construction Cost: $200,000.00
Issue for Bid: April 9, 2015
Bid Opening: April 30, 2015
Award of Contract: May 20, 2015
Start of Construction: July 1, 2015

Modifications for Freezer, Garst Dining Center
Additional freezer storage space is needed at the Garst Dining Center. In order to accommodate a new outdoor freezer, a new pad will be provided and existing site features modified as required. Work for the project includes expansion of an existing screen wall, a new concrete pad and electrical service for operation of a new freezer. Work would be accomplished during the summer of 2015.

Consultant: TBD
Estimated Construction Cost: $150,000
Issue for Bid: April 22, 2015
Bid Opening: May 7, 2015
Award of Contract: May 20, 2015
Start of Construction: May 20, 2015